Contractors, draws, and staying in control
Three bids on one scope, work before money, changes in writing, and a weekly walk — the people system that prevents the #1 cause of first-flip losses without turning you into anyone's adversary.
Contractor failure ruins more first flips than bad markets ever have — and nearly all of it is preventable with structure you now already own: the Lesson 9 scope. This lesson turns it into a hiring process, a payment architecture, and a weekly rhythm. The goal isn't suspicion; it's a system so clean that everyone can be trusted because nobody has to be.
Hiring: the referral economy plus one test
Good contractors are booked, not Googling — find them where they already work: other investors' crews (your REIA and buyer-list network), the supply-house counter ("who buys in volume and pays their account?"), inspectors and agents who see workmanship after the fact, and clean job sites you stop at. Verify like an underwriter — license and insurance called in, references old and new — then run the professional's move: a small paid test project ($3–5k bath or a punch-list week) before anyone touches your full renovation. → The complete hiring system
Bid it three ways, one scope. Identical scope to three contractors makes bids finally comparable. Toss the outlier 25% below the cluster — that's not a bargain, it's a change-order business plan — and interrogate line-level gaps: they're showing you where your scope was vague.
The payment architecture
One principle runs everything: completed work releases money; money never advances ahead of work.
- 01Deposit: 0–10%, mobilization onlyBig deposits fund the contractor's PREVIOUS client's project — the oldest story in renovation. Materials go on your own supplier accounts where possible: transparency, and the markup-and-float game dies.
- 02Draws at milestones, after YOUR walkDemo + rough-in passed inspection → draw. Drywall/paint done → draw. Finishes set → draw. The Lesson 9 build order is the schedule; your eyes are the trigger; the walk happens within 24 hours of the request because fast honest payment is your half of the deal.
- 0310% retainage to the very endThe punch list gets finished because it's worth $5,000 — the only leverage that survives to the end of any project. Release it with the final lien waiver in hand.
- 04Lien waivers with every checkPartial waiver per draw, final waiver at completion — the paper that prevents an unpaid sub from clouding your title at the sale you're doing all this for.
- 05Changes exist only in writingA signed change order with a price and a schedule impact — before the work, every time, no matter how small or how friendly. Verbal changes are where budgets dissolve; a pad of blank forms on site is the cheapest insurance ever printed.
The weekly rhythm
One scheduled walk (same day weekly, against the scope, photographing everything — especially inside walls before they close: that photo file settles disputes, feeds your variance data, and documents your build for the appraiser and buyer's inspector later). One channel for all decisions and selections — texts scatter; a single thread holds the record. Selections delivered ahead of need — your slow tile decision is his idle crew, and the owner is every schedule's most common bottleneck. And pay earned draws same-day — contractors triage clients by payment reliability, and the investor who inspects promptly and pays instantly gets the callback, the honest number, and the crew in January. That reputation compounds across every project you'll ever run; it's the repeatable-crew asset this whole business is secretly building.
The pitfall to skip: managing by relationship instead of by document because the contractor is likable. The likable ones deserve the clean system too — it's what lets you hire them again with the friendship intact.
Do this now: Build your one-page contract checklist from this lesson (scope attached · fixed price · draw schedule · written changes only · timeline with daily late credit · lien waivers · insurance verified) and have a local attorney review your template once. It'll cost a few hundred dollars and govern a decade of projects.